Grid Connection Code and Renewable Licensing Procedures

Implements the Renewable Energy Licensing Regulation 2026, setting deadlines for grid connection studies and simplified rules for the Rimal Solar Development…

Reference
Ministerial Resolution No. 8/2026
Year
2026
Status
in force
Ministry
Ministry of Energy and Natural Resources

Provisions

  • The grid operator delivers the connection study within 20 working days of a complete request.
  • Plots in the Rimal Solar Development Zone are pre-approved for land use and environmental pre-screening.
  • Self-consumption systems below 1 MW are registered with the grid operator and surplus energy is credited through net billing.
  • Generation licences between 1 and 50 MW are granted for 25 years, renewable.