Grid Connection Code and Renewable Licensing Procedures
Implements the Renewable Energy Licensing Regulation 2026, setting deadlines for grid connection studies and simplified rules for the Rimal Solar Development…
- Reference
- Ministerial Resolution No. 8/2026
- Year
- 2026
- Status
- in force
- Ministry
- Ministry of Energy and Natural Resources
Provisions
- The grid operator delivers the connection study within 20 working days of a complete request.
- Plots in the Rimal Solar Development Zone are pre-approved for land use and environmental pre-screening.
- Self-consumption systems below 1 MW are registered with the grid operator and surplus energy is credited through net billing.
- Generation licences between 1 and 50 MW are granted for 25 years, renewable.